Before proceeding with the first switch-on, it is recommended to check the installation, the electrical connections including the signal cable tightness check and the cable tightness check
power and installation environment. Then proceed with the first start-up and the general UPS check, which includes: synchronism check, mains/inverter switching and vice versa, bypass test, operation check, options, battery self-test, genset test if present.
Autonomy test with actual load - battery charger, UPS measurement check.